| | Ground level Signal Box upgrade | |
| There is an ongoing project to install a fully
working lever controlled signalling system for the ground level track. |
| Controlling the Signals and Points. |
| A signal lever unit is being modified and
extensively altered to enable it to be used on the ground level track to control signals and points, all operated from the signal box. |
| It will operate with a combination of low voltage
(24 volt) electricity and pneumatic (air) operated rams moving the signals and points. A compressed air ring main will feed the system from an air reservoir located in the signal box. |
![]() |
![]() |
![]() |
| Club members David & Norman working on the lever unit modifications. |
![]() |
| This shows the unit at the end of October
2004. Danny & David are busy fitting and wiring the micro switches. |
![]() |
| A closer view of the unit as of 31st October 2004. |
![]() |
| By the middle of November the main lever wiring
was well underway, the unit has been partly dismantled for painting (the levers are not attached). |
![]() |
| Another view which includes the lever base unit. |
![]() |
| 19th December 2004. The signal lever frame is moved into the signal box. |
![]() |
| The frame being positioned before fixing down. |
![]() |
| The frame is now in place. |
![]() |
| The first lever has been positioned to check alignment before the rest are fitted. |
![]() |
| More progress on fitting the individual levers. |
![]() |
| This shows the micro switches and solenoids in place. |
![]() |
| As of 9th January 2005 |
![]() |
| On the 9th January 2005, club members were given
a talk on how the system will operate by Dave, one of the projects designers. |
![]() |
| Dave explaining the layout of a Signal Gantry, which will span the tracks. |
| By July 2005 a lot of unseen work had been
completed, including more wiring to the signal lever unit and the first 'points' motor installed and connected. |
![]() |
| Situated just outside the signal box, this is the
first points motor in place, which has been installed to test the various electrical and air systems. |
| By April 2006 a lot more work had been done
including an extensive underground trunking system, to carry both electrical cable and air supplies to the signal positions. |
![]() |
![]() |
![]() |
| The wiring for the signal levers has also progressed well. |
| Progress has been going well and by July 2006
more wiring and air lines have been installed, also more connections have been made to the signal levers. |
![]() |
![]() |
![]() |