Raised Track Re-Alignment Project 2007
 
| Return to Main Picture Galley Page |
Horizontal Line
Over the last few years to raised track at Ridgeway Park has moved due to changes in the soil
water table etc.
In early January 2007 work started on not only re-aligning the track but also refurbishing the layout
and replacing the damaged and decaying wooden sleepers.
As the track is far to long to be done in one go the worst section was tackled first.
The deadline for completion was the end of March, as the track had to be ready

for the first public passenger hauling afternoon on the 1st of April.
Starting to remove the track sections from the metal support frame.
Removing Track Sections
 
Not all the track wanted to be removed.
Temoving Track
 
Section of Track
 
Track sections being moved to the work area.
Moving Track to Work Area
 
Unloading Track
 
Track ready for refurbishing.
Track waiting for Attention
Up Arrow
Removing sleepers that need replacing.
Removing Damaged Sleepers
 
Using a specially made Jig, new sleepers blanks were routed to form slots for the rail.
Making New Sleeprs
 
Sleepers
 
the slots in the sleeper enables very accurate track spacing to be maintained.
New Sleeper Fitted
 
Fitting the new sleepers.
Sleepers Being Positioned
 
The sleepers were then treated with preserver.
Wood Work Being Painted
Up Arrow
More Painting
 
All the now exposed metal support rail was also painted (this area has not yet been re-aligned)
Painting the Supports
 
Re-aligning the concrete track columns and metal support rail.
Realigning the Track
 
One of the columns being re-aligned.
Track Column
 
Progress on Layout
 
One of the support joints ready for final assembly.
Support Joint
Up Arrow
 Final alignment at one of the track support joints.
Final Alignment
 
Refurbished track ready for re-fitting (on the support in the background).
Ready for Fixing
 
Fixing track sections to the metal supports.
Fixing the Track Down
 
More Fixing
 
Some of the 'Track Gang', taking a well earned Tea Break.
Track Gang
 
The finished track ready for use.
Track in Place
 
One of the track joints showing some of the wiring for the signals.
Track Joint
 
One of the club steam Locomotives running on the track on 1st April 2007
Steram on the Track
Due to the sterling efforts of a dedicated team of club members a large section
of the raised track has been fully refurbished, re-aligned and completed
in time for our first public running session of the summer.
-0-
 