Patsy McGlone
27th June 2012
Written Answer from the Minister for Regional Development
NI Water Sewage and Water
Schemes
Mr Patsy McGlone (Mid Ulster):
To ask the Minister for Regional Development to detail the current NI Water
sewage and water schemes which have had work stopped or remain incomplete
due to the lack of continuing finance.
(AQW
13014/11-15)
Minister for Regional Development: I have been advised by
Northern Ireland Water (NIW) that no water or sewerage schemes have had work
stopped or remain incomplete due to lack of continuing finance and all
schemes currently at construction stage will be completed within planned
funding levels.
As a result of revised Public Expenditure (PE) funding a number of schemes
that were planned for delivery during the three year Price Control period
ending March 2013 have been deferred to the following Price Control period
which covers the two years ending March 2015. However, NIW has not altered
the funding level allocated to water infrastructure as a result of the
revised PE funding.
ENDS
|